Presentation + Paper
9 July 2018 GLT receiver commissioning at JCMT and future JCMT instrumentation
Dan Bintley, Per Friberg, Ryan Berthold, Tim Chuter, Kuan-Yu Liu, Craig Walther, Jessica Dempsey, Paul Ho, Helen McGregor, Satoki Matsushita, Keiichi Asada, Shoko Koyama, Hiroaki Nishioka, Chih-Chiang Han, Chih-Wei Huang, Lupin Lin, Ta-Shun Wei, Derek Kubo, Ranjani Srinivasan, Ramprasad Rao, Geoff Bower, Peter Oshiro, Ming-Tang Chen
Author Affiliations +
Abstract
The Greenland Telescope (GLT) project and the East Asian Observatory (EAO) successfully commissioned the first light GLT instrument at the James Clerk Maxwell Telescope (JCMT) in Hawaii, prior to transferring the instrument to Greenland. The GLT instrument which comprises of a cryostat with three cartridge-type receivers (at 86GHz, 230GHz and 345GHz) was installed into the receiver cabin of JCMT and operated in three modes: - (a) Regular JCMT observing with the GLT instrument, using ACSIS, (JCMT’s autocorrelation spectrometer) as the backend and JCMT software for telescope control, data reduction, pointing and antenna focus adjustment. (b) Single dish observations of astronomical spectral line sources, recording data onto mark 6 recorders for offline data reduction. (c) eSMA interferometer array observations at 230GHz in conjunction with the SMA. In this paper, we report on the installation and integration of the GLT instrument at JCMT, present results from commissioning and show how the success of the GLT instrument commissioning fits with our plans for future instrumentation at JCMT.
Conference Presentation
© (2018) COPYRIGHT Society of Photo-Optical Instrumentation Engineers (SPIE). Downloading of the abstract is permitted for personal use only.
Dan Bintley, Per Friberg, Ryan Berthold, Tim Chuter, Kuan-Yu Liu, Craig Walther, Jessica Dempsey, Paul Ho, Helen McGregor, Satoki Matsushita, Keiichi Asada, Shoko Koyama, Hiroaki Nishioka, Chih-Chiang Han, Chih-Wei Huang, Lupin Lin, Ta-Shun Wei, Derek Kubo, Ranjani Srinivasan, Ramprasad Rao, Geoff Bower, Peter Oshiro, and Ming-Tang Chen "GLT receiver commissioning at JCMT and future JCMT instrumentation", Proc. SPIE 10708, Millimeter, Submillimeter, and Far-Infrared Detectors and Instrumentation for Astronomy IX, 1070815 (9 July 2018); https://doi.org/10.1117/12.2313083
Lens.org Logo
CITATIONS
Cited by 1 scholarly publication.
Advertisement
Advertisement
RIGHTS & PERMISSIONS
Get copyright permission  Get copyright permission on Copyright Marketplace
KEYWORDS
Receivers

Telescopes

Mirrors

Polarization

Calibration

Antennas

Astronomy

RELATED CONTENT

The Australian SKA Pathfinder
Proceedings of SPIE (September 17 2012)
Constructing the EVLA while operating the VLA
Proceedings of SPIE (July 28 2010)
Overview of engineering activities at the SMA
Proceedings of SPIE (July 12 2008)
The ALMA OT in early science: supporting multiple customers
Proceedings of SPIE (September 24 2012)
ALMA: the first year of observations
Proceedings of SPIE (September 13 2012)

Back to Top