The Rubin Observatory Commissioning Camera (ComCam) is a scaled down (144 Megapixel) version of the 3.2 Gigapixel LSSTCam which will start the Legacy Survey of Space and Time (LSST), currently scheduled to start in 2024. The purpose of the ComCam is to verify the LSSTCam interfaces with the major subsystems of the observatory as well as evaluate the overall performance of the system prior to the start of the commissioning of the LSSTCam hardware on the telescope. With the delivery of all the telescope components to the summit site by 2020, the team has already started the high-level interface verification, exercising the system in a steady state model similar to that expected during the operations phase of the project. Notable activities include a simulated “slew and expose” sequence that includes moving the optical components, a settling time to account for the dynamical environment when on the telescope, and then taking an actual sequence of images with the ComCam. Another critical effort is to verify the performance of the camera refrigeration system, and testing the operational aspects of running such a system on a moving telescope in 2022. Here we present the status of the interface verification and the planned sequence of activities culminating with on-sky performance testing during the early-commissioning phase.
KEYWORDS: Observatories, System integration, Imaging systems, Data processing, Data acquisition, Control systems, Cameras, Telescopes, Image processing, Software development
The Rubin Observatory has entered its latter stages of the construction effort with system integration, test and commissioning. All system elements are coming together including components of the telescope, the science camera and software systems for control and data processing. In this paper we report on the progress, status, plans and schedule for integrating the system elements into a fully functional observatory to carry out the 10-year Legacy Survey of Space and Time.
In the last couple of years, the Rubin telescope and site subsystem has made tremendous progress and overcome a few challenges. The insulated cladding on the dome is done and work is now focused on finishing the louvers, weatherproof cladding, interior work, light baffles, and the final fabrications. This has been done concurrently with the installation of the telescope mount, now mostly complete and approaching the beginning of functional testing in September-October, 2022. While work is being done on these two major subsystems, other major components and systems are being integrated and tested in a system spread configuration: M1M3 & M2 mirrors, the camera hexapod/rotator and the control software, including elements of the active optics control and the commissioning camera. Finally, the calibration system - an important contributor to achieving the exquisite photometry required by the Legacy Survey of Space and Time (LSST) - is being finalized.
The construction of the Vera C. Rubin Observatory is well underway, and when completed the telescope will carry out a precision photometric survey, scanning the entire sky visible from Chile every three days. The photometric performance of the survey is expected to be dominated by systematics; therefore, multiple calibration systems have been designed to measure, characterize and compensate for these effects, including a dedicated telescope and instrument to measure variations in the atmospheric transmission over the LSST bandpasses. Now undergoing commissioning, the Auxiliary Telescope system is serving as a pathfinder for the development of the Rubin Control systems. This paper presents the current commissioning status of the telescope and control software, and discusses the lessons learned which are applicable to other observatories.
The Vera C. Rubin Observatory is a joint NSF and DOE construction project with facilities distributed across multiple sites. These sites include the Summit Facility on Cerro Pachón, Chile; the Base Facility in La Serena, Chile; the Project and Operations Center in Tucson, AZ; the Camera integration and testing laboratories at SLAC National Accelerator Laboratory in Menlo Park, CA; and the data support center based at the National Center for SuperComputing Applications at Urbana-Champaign, IL. The Rubin Observatory construction Project has entered its system integration and testing phase where major subsystem components are coming together and being tested and verified at a system level for the first time. The system integration phase of the Project requires a closely coordinated and organized plan to merge, manage, and be able to adapt the complex set of subsystems and activities across the entire observatory as real effects are discovered. In this paper we present our strategy to successfully complete integration, test and commissioning of the systems making up the Rubin Observatory. We include discussion on (i) our strategy for integration activities and the verification of requirements (ii) a brief summary of construction status at the time of this paper, (iii) early integration activities that are used to mitigate risks including the use of the Rubin Observatory's commissioning camera (ComCam), planning for the integration, testing and verification of the primary science instrument - LSSTCam, and lastly, (v) Science Verification through short concentrated survey-like campaigns. Throughout this paper we identify where key performance metrics are addressed that directly impact the Rubin Observatory's 10{year Legacy Survey of Space and Time (LSST) science capabilities - e.g. image quality, telescope dynamics, alert latency, etc...
The Vera C. Rubin Observatory (Rubin Obs) (formerly Large Synoptic Survey Telescope - LSST) is an 8.4-m telescope, now under construction in Chile. In the last couple of years, the telescope has achieved tremendous progress, though like many other projects, progress has been curtailed for over six months due to the worldwide pandemic. This paper provides the high-level status of each of the telescope's subsystem. The summit facility (Cerro Pachon) and base facility (La Serena) have been substantially completed. The dome is expected to be finished by October of 2021, which will also allow the completion of integration and testing of the Telescope Mount Assembly (TMA). The integration and verification of the TMA is planned to be completed by the end of 2021. The two mirror systems, M1M3 and M2, have been fully tested under interferometers, showing they both satisfy their performance requirement, and both have been received at the summit facility. The M2 mirror has been successfully coated with protected aluminum, which is the first scientific coating produced by the new Rubin coating plant. The M1M3 mirror is planned to be coated with the same plant at the beginning of 2022. The auxiliary telescope and its principal spectrograph instrument, which will allow for real-time atmospheric characterization, has been commissioned. The Rubin environment awareness system (EAS), which includes the DIMM, weather station, all-sky camera, and facility environmental control, is operational. Significant progress has been made on the software for all of the above-mentioned subsystems, as well as the comprehensive telescope control system and the telescope operator interfaces.
Rubin Observatory’s Commissioning Camera (ComCam) is a 9 CCD direct imager providing a testbed for the final telescope system just prior to its integration with the 3.2-Gigapixel LSSTCam. ComCam shares many of the same subsystem components with LSSTCam in order to provide a smaller-scale, but high-fidelity demonstration of the full system operation. In addition, a pathfinder version of the LSSTCam refrigeration system is also incorporated into the design. Here we present an overview of the final as-built design, plus initial results from performance testing in the laboratory. We also provide an update to the planned activities in Chile both prior to and during the initial first-light observations.
KEYWORDS: Large Synoptic Survey Telescope, Imaging systems, System integration, Cameras, Telescopes, Observatories, Data processing, Interfaces, Control systems, Computing systems
The Commissioning Phase of the LSST Project is the final stage in the combined NSF and DOE funded LSST construction project. The LSST commission phase is planned to start early in 2020 and be completed near the end of 2022, ending with the LSST Observatory system ready to start survey operations. Commissioning includes the assembly of the three principal subsystems (Telescope, Camera and Data Management) into the LSST Observatory System and the integration and test (AI&T) efforts as well as the science verification activities. The LSST System AI&T and Commissioning Plan is driven by a combination of engineering and scientifically oriented activities to show compliance with technical requirements and readiness to conduct science operations (acquiring data, processing data, and serving data and derived data products to users). LSST System AI&T and Commissioning will be carried out over four phases of activity: Phase-0) Pre-commissioning preparations (work breakdown structure; Phase-1) Early System AI&T with a commissioning camera (ComCam); Phase-2) Full System AI&T when the LSST Science Camera is shipped to Chile, integrated on the telescope and the data management system (DMS) is exercised with full scale data; and Phase-3) Science Validation where a series of mini-surveys are used to characterize the system with respect to the survey performance specifications in the SRD/LSR and functionality of the, leading to operations readiness. The Science Validation Phase concludes with an Operations Readiness Review (ORR).
The LSST System Assembly, Integration and Test and Commissioning effort has been planned out over several phases The first phase of commissioning under Early AI&T is designed to test and verify the system level interfaces using ComCam – a 144Mpixel imager utilizing the same control components as the full science camera. During this period, the telescope active optics system will be brought into compliance with system requirements; the scheduler will be exercised and all safety checks verified for autonomous operation; and early DM algorithm testing will be performed with on-sky data from ComCam using a commissioning computing cluster at the Base Facility.
The second phase of activities under Full System AI&T is designed to complete the technical integration of the three principal subsystems and EPO, show full compliance with system level requirements as detailed in the Observatory System Specifications and system level interface control documents, and provide full scale data for further DM/EPO software and algorithmic testing and development. System level requirements that flow directly to subsystems without any further derivation will be tested for compliance, at the subsystem level and below, under the supervision of Project Systems Engineering. This document includes the general approach and goals for these tests. It is expected that roughly four (4) months into the Full System AI&T phase the telescope and camera will be fully integrated and routinely producing science grade images over the full field of view (FOV), at which point “System First Light” will be declared. Following System First Light will be an intensive data acquisition period design to test the image processing pipelines and validate the derived science products that are to be delivered by the LSST survey.
The third and final phase of activities under Science Validation is designed to fully characterize the system performance specifications detailed in LSST System Requirements Document and the range of demonstrated performance per the LSST Science Requirements. These activities are based on the measured “On-Sky” performance and informed simulations of the LSST system.
In this paper we describe the inputs and assumptions to the commissioning plan, a summary of the activities in each phase, management strategies and expected outcomes.
The Large Synoptic Survey Telescope (LSST) Commissioning Camera (ComCam) is a smaller, simpler version of the full LSST camera (LSSTCam). It uses a single raft of 9 (instead of twenty-one rafts of 9) 4K x 4K LSST Science CCDs, has the same plate scale, and uses the same interfaces to the greatest extent possible. ComCam will be used during the Project’s 6-month Early Integration and Test period beginning in 2020. Its purpose is to facilitate testing and verification of system interfaces, initial on-sky testing of the telescope, and testing and validation of Data Management data transfer, infrastructure and algorithms prior to the delivery of the full science camera.
We present the design and lab performance of the Parallel Imager for Southern Cosmology Observations (PISCO), a photometer for the 6.5 m diameter Magellan telescopes that produces gl, rl, il, and zl band images simulta- neously within a 9 arcminute field of view. This design provides efficient follow-up observations of faint sources, particularly galaxy clusters and supernovae. Simultaneous imaging speeds the observing cadence by at a factor
of ~ 3 (including optical losses) compared to other photometric imagers. Also, the determination of color (flux
ratio between bands) is relatively immune to time variations in gray opacity due to clouds, so observations can
proceed in less than optimal conditions. First light is expected in September 2014 2014.
KEYWORDS: Control systems, Sensors, Telescopes, Data archive systems, Antennas, Human-machine interfaces, Bolometers, Data acquisition, Detection and tracking algorithms, Data storage
We present the software system used to control and operate the South Pole Telescope. The South Pole Telescope is
a 10-meter millimeter-wavelength telescope designed to measure anisotropies in the cosmic microwave background
(CMB) at arcminute angular resolution. In the austral summer of 2011/12, the SPT was equipped with a new
polarization-sensitive camera, which consists of 1536 transition-edge sensor bolometers. The bolometers are read
out using 36 independent digital frequency multiplexing (DfMux) readout boards, each with its own embedded
processors. These autonomous boards control and read out data from the focal plane with on-board software
and firmware. An overall control software system running on a separate control computer controls the DfMux
boards, the cryostat and all other aspects of telescope operation. This control software collects and monitors
data in real-time, and stores the data to disk for transfer to the United States for analysis.
Access to the requested content is limited to institutions that have purchased or subscribe to SPIE eBooks.
You are receiving this notice because your organization may not have SPIE eBooks access.*
*Shibboleth/Open Athens users─please
sign in
to access your institution's subscriptions.
To obtain this item, you may purchase the complete book in print or electronic format on
SPIE.org.
INSTITUTIONAL Select your institution to access the SPIE Digital Library.
PERSONAL Sign in with your SPIE account to access your personal subscriptions or to use specific features such as save to my library, sign up for alerts, save searches, etc.