NASA's Technology Readiness Level (TRL)-6 is documented for the James Webb Space Telescope (JWST) Wavefront
Sensing and Control (WFSC) subsystem. The WFSC subsystem is needed to align the Optical Telescope Element
(OTE) after all deployments have occurred, and achieves that requirement through a robust commissioning sequence
consisting of unique commissioning algorithms, all of which are part of the WFSC algorithm suite. This paper identifies
the technology need, algorithm heritage, describes the finished TRL-6 design platform, and summarizes the TRL-6 test
results and compliance. Additionally, the performance requirements needed to satisfy JWST science goals as well as the
criterion that relate to the TRL-6 Testbed Telescope (TBT) performance requirements are discussed.
The primary mirror of the James Webb Space Telescope (JWST) consists of 18 segments and is 6.6 meters in diameter.
A sequence of commissioning steps is carried out at a single field point to align the segments. At that single field point,
though, the segmented primary mirror can compensate for aberrations caused by misalignments of the remaining
mirrors. The misalignments can be detected in the wavefronts of off-axis field points. The Multifield (MF) step in the
commissioning process surveys five field points and uses a simple matrix multiplication to calculate corrected positions
for the secondary and primary mirrors. A demonstration of the Multifield process was carried out on the JWST Testbed
Telescope (TBT). The results show that the Multifield algorithm is capable of reducing the field dependency of the TBT
to about 20 nm RMS, relative to the TBT design nominal field dependency.
The one-meter Testbed Telescope (TBT) has been developed at Ball Aerospace to facilitate the
design and implementation of the wavefront sensing and control (WFSC) capabilities of the
James Webb Space Telescope (JWST). We have recently conducted an "end-to-end"
demonstration of the flight commissioning process on the TBT. This demonstration started with
the Primary Mirror (PM) segments and the Secondary Mirror (SM) in random positions,
traceable to the worst-case flight deployment conditions. The commissioning process detected
and corrected the deployment errors, resulting in diffraction-limited performance across the
entire science FOV. This paper will describe the commissioning demonstration and the WFSC
algorithms used at each step in the process.
The one-meter Testbed Telescope (TBT) has been developed at Ball Aerospace to facilitate the
design and implementation of the wavefront sensing and control (WFS&C) capabilities of the
James Webb Space Telescope (JWST). The TBT is used to develop and verify the WFS&C
algorithms, check the communication interfaces, validate the WFS&C optical components and
actuators, and provide risk reduction opportunities for test approaches for later full-scale
cryogenic vacuum testing of the observatory. In addition, the TBT provides a vital opportunity
to demonstrate the entire WFS&C commissioning process. This paper describes recent WFS&C
commissioning experiments that have been performed on the TBT.
KEYWORDS: James Webb Space Telescope, Mirrors, Wavefront sensors, Observatories, Space operations, Databases, Optical components, Cameras, Wavefronts, Error control coding
The opto-mechanical design of the 6.6 meter James Webb Space Telescope (JWST), with its actively-controlled secondary and 18-segment primary mirror, presents unique challenges from a system engineering perspective. To maintain the optical alignment of the telescope on-orbit, a process called wavefront sensing and control (WFS&C) is employed to determine the current state of the mirrors and calculate the optimal mirror move updates. The needed imagery is downloaded to the ground, where the WFS&C algorithms to process the images reside, and the appropriate commands are uploaded to the observatory. Rather than use a dedicated wavefront sensor for the imagery as is done in most other applications, a science camera is used instead.
For the success of the mission, WFS&C needs to perform flawlessly using the assets available among the combination of separate elements (ground operations, spacecraft, science instruments, optical telescope, etc.) that cross institutional as well as geographic borders. Rather than be yet another distinct element with its own set of requirements to flow to the other elements as was originally planned, a novel approach was selected. This approach entails reviewing and auditing other documents for the requirements needed to satisfy the needs of WFS&C. Three actions are taken: (1) when appropriate requirements exist, they are tracked by WFS&C ; (2) when an existing requirement is insufficient to meet the need, a requirement change is initiated; and finally (3) when a needed requirement is missing, a new requirement is established in the corresponding document. This approach, deemed a "best practice" at the customer's independent audit, allows for program confidence that the necessary requirements are complete, while still maintaining the responsibility for the requirement with the most appropriate entity.
This paper describes the details and execution of the approach; the associated WFS&C requirements and verification documentation; and the implementation of the primary database tool for the project, DOORS (Dynamic Object-Oriented Requirements System).
From its orbit around the Earth-Sun second Lagrange point some million miles from Earth, the James Webb Space Telescope (JWST) will be uniquely suited to study early galaxy and star formation with its suite of infrared instruments. To maintain exceptional image quality using its 6.6 meter segmented primary mirror, wavefront sensing and control (WFS&C) is vital to ensure the optical alignment of the telescope throughout the mission.
WFS&C design architecture includes using the Near-Infrared Camera (NIRCam) to provide imagery for ground-resident image processing algorithms which determine the optimal alignment of the telescope. There are two distinct mission phases for WFS&C, both of which use algorithms and NIRCam imagery to determine the required segment updates. For the first phase, WFS&C commissioning, the telescope is taken from its initial deployed state with each of the 18 primary mirror segments acting like independent telescopes, to its final phased state with each segment acting in concert as a part of a single mirror. The second phase, Wavefront Monitoring and Maintenance, continues for the rest of the mission. Here the wavefront quality is evaluated, and when needed, the mirror positions are updated to bring it back to an optimal configuration.
This paper discusses the concept of operations for the commissioning and on-going maintenance of the telescope alignment using WFS&C.
Access to the requested content is limited to institutions that have purchased or subscribe to SPIE eBooks.
You are receiving this notice because your organization may not have SPIE eBooks access.*
*Shibboleth/Open Athens users─please
sign in
to access your institution's subscriptions.
To obtain this item, you may purchase the complete book in print or electronic format on
SPIE.org.
INSTITUTIONAL Select your institution to access the SPIE Digital Library.
PERSONAL Sign in with your SPIE account to access your personal subscriptions or to use specific features such as save to my library, sign up for alerts, save searches, etc.